Friday, July 17, 2009
Delays!
Sorry for the delay in my posts, things have been hectic around here lately ~!
Will resume posting next week.
Enjoy the days!
Sunday, July 12, 2009
Earned Value Worksheet
Hi everyone,
Technorati Claim Post
Tuesday, July 7, 2009
Project, Portfolio, Program, Process, Operation.. what's the difference? We're all managers!
Monday, July 6, 2009
Feedback on the technical set up of this blog and feed!
Sunday, July 5, 2009
Overview of Processes by Knowledge Area
Project Integration Management | Develop project charter (initiating) Develop project management plan (planning) Direct and manage project execution (executing) Monitor and control project work (monitor and control) Perform integrated change control (monitor and control) Close project or phase (closing) |
Project Scope Management | Collect requirements (planning) Define scope (planning) Create WBS (planning) Verify scope (monitor and control) Control scope (monitor and control) |
Project Time Management | Define activities (planning) Sequence activities (planning) Estimate activity resources (planning) Estimate activity durations (planning) Develop schedule (planning) Control schedule (monitor and control) |
Project Cost Management | Estimate costs (planning) Determine budget (planning) Control costs (monitor and control) |
Project Quality Management | Plan quality (planning) Perform quality assurance (executing) Perform quality control (monitor and control) |
Project Human Resource Management | Develop human resource plan (planning) Acquire project team (executing) Develop project team (executing) Manage project team (executing) |
Project Communications Management | Identify Stakeholders (initiating) Plan communications (planning) Distribute information (executing) Manage stakeholder expectations (executing) Report performance (monitor and control) |
Project Risk Management | Plan risk management (planning) Identify risks (planning) Perform qualitative risk analysis (planning) Perform quantitative risk analysis (planning) Plan risk responses (planning) Monitor and control risks (monitor and control) |
Project Procurement Management | Plan procurements (planning) Conduct procurements (executing) Administer procurements (monitor and control) Close procurements (closing) |
Saturday, July 4, 2009
Overview of Project Process Groups
Initiating Develop Project Charter (integration) Identify Stakeholders (communications) Planning Develop Project Management Plan (integration) Collect Requirements (scope) Define Scope (scope) Create WBS (scope) Define Activities (time) Sequence Activities (time) Estimate Activity Resources (time) Estimate Activity Durations (time) Develop Schedule (time) Estimate Costs (cost) Determine Budget (cost) Plan Quality (quality) Develop Human Resource Plan (human resource) Plan Communications (communications) Plan Risk Management (risk) Identify Risks (risk) Perform Qualitative Risk Analysis (risk) Perform Quantitative Risk Analysis (risk) Plan Risk Responses (risk) Plan Procurements (procurement) Executing Direct and Manage Project Execution (integration) Perform Quality Assurance (quality) Acquire Project Team (human resource) Develop Project Team (human resource) Manage Project Team (human resource) Distribute Information (communications) Manage Stakeholder Expectations (communications) Conduct Procurements (procurement) Monitoring and Controlling Monitor and Control Project Work (integration) Perform Integrated Change Control (integration) Verify Scope (scope) Control Scope (scope) Control Schedule (time) Control Costs (cost) Perform Quality Control (quality) Report Performance (communications) Monitor and Control Risks (risk) Administer Procurements (procurement) Closing Close Project or Phase (integration) Close Procurements (procurement)
PMP - My Lessons Learned
As for my Lessons Learned:
I used Head First PMP and PMBOK, studied both somewhat intermittently over
two months, but really didn't lean into it to say the least. (kept
reading the same chapters over and over again, thinking THIS time I'll
actually start studying!)
The two weekends leading up to the exam:
1. Went camping about three km away from any civilization, just me,
the ocean and the PMBOK! Made it through all the knowledge areas
twice and made some crude notes.
2. Had to go to Vancouver to write the PMP exam on Monday (today)
so decided to go over on Friday night and lock myself in a hotel room
and study the last bits. I read all the areas that I was the least
bit unsure of, focusing particularly on risk, earned value management (EVT), and procurement. I
did several of the 50 question sample exams from Head First PMP web site,
and all of the exercises in the Head First PMP book. I focused heavily on
EVT and understanding what the various charts and graphical
representations are for. (Pareto, Decision Tree etc. etc)
By Sunday night, I was feeling pretty good.
In the exam first thing on Monday morning, I wasn't feeling the same
for the start, but then it got better.
Overall, if I was doing it again, I would focus more on the ITTOs, and
page 70 of the PMBOK.
The exam was challenging, and certainly you want to have read the
PMBOK at least twice, THEN use some other resources.
Earned Value Formulas
Acronym | Term | Formula | Description |
---|---|---|---|
CV | Cost Variance | CV = EV - AC | CV is the cost performance and helps determine whether the project is executing as planned. Subtracting AC from EV calculates the cost variance. |
SV | Schedule Variance | SV = EV - PV | SV indicates the schedule performance of the project. This value can indicate whether the project work is proceeding as planned. Calculate the SV by subtracting the PV from the EV. |
CPI | Cost Performance Index | CPI = EV / AC | For the CPI, divide EV by AC. Cost performance index allows the project manager to see where they're at on the budget; a CPI greater than one indicates the project over budget, while a CPI lower than one indicates under budget. |
SPI | Schedule Performance Index | SPI = EV / PV | Project managers can use the SPI to help predict when their projects will be completed. To calculate the SPI, divide EV by PV. An SPI of one indicates the project is on schedule, greater than one indicates it is ahead of schedule; and lower than one indicates it is behind schedule. |
EAC | Estimate at Completion | EAC = BAC / CPI EAC = AC + ETC EAC = AC + (BAC - EV) | EAC is used by project managers to give their best estimate of the total costs of projects based on perofmance to date. The simplest formula to remember for EAC is BAC/CPI. |
ETC | Estimate to Complete | ETC = EAC - AC | ETC is the estimated cost to execute the remaining work for the project (or phase, sub-project. ETC helps project managers predict what the final cost of the project will be upon completion. |
VAC | Variance at Completion | VAC = BAC - EAC | VAC is the difference between the budget at completion and the expected total costs of the project based on current performance. |